Multiple Choice
A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths in this network.
E) There are six paths in this network.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: In PERT analysis, the identification of the
Q46: PERT, but not CPM, has the ability
Q50: Slack is the amount of time an
Q53: Define slack time.
Q109: Consider the network presented in the following
Q110: Which of the following statements regarding Gantt
Q111: The beta distribution is used in project
Q113: The waterfall approach is used most often
Q117: An activity on a PERT network has
Q119: A partially solved PERT problem is detailed