Multiple Choice
Which of the following statements regarding PERT times is true?
A) The optimistic time estimate is an estimate of the minimum time an activity will require.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) .
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Ill-defined projects are typified by software development
Q32: An activity on a PERT network has
Q45: Work breakdown structure is a useful tool
Q57: The expected activity time in PERT analysis
Q88: If an activity whose normal duration is
Q91: Which of the following projects were completed
Q96: The difference between AON and AOA networks
Q98: The project organization works best when which
Q105: Project managers have their own code of
Q120: How is the expected completion time of