A local project being analyzed by PERT has 42 activities,13 of which are on the critical path.If the estimated time along the critical path is 105 days with a project variance of 25,what is the probability that the project will be completed in 95 days or less?
A) -0.4
B) 0.0228
C) 0.3444
D) 0.9772
E) 4.2
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Gantt charts give a timeline for each
Q31: One responsibility of a project manager is
Q32: An activity on a PERT network has
Q96: The difference between AON and AOA networks
Q98: The project organization works best when which
Q103: Activity R on a CPM network has
Q104: The _ has established a code of
Q105: Which of the following is NOT performed
Q106: Given the critical path below,calculate the following:<br>a.The
Q127: Agile project management is a type of