Essay
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:

Verified
(a)$2,000; (b)$4,000...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q5: An activity on a PERT network has
Q13: If an activity whose normal duration is
Q21: The phases of project management are:<br>A) planning,
Q35: What is the basic difference between PERT
Q37: WBS stands for which of the following
Q46: PERT, but not CPM, has the ability
Q74: Ethical issues that may arise in projects
Q80: A code of ethics especially for project
Q105: Which of the following is NOT performed
Q109: A project organization:<br>A) is effective for companies