Multiple Choice
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.
-Using the information in Table J.1 and the SPT rule, what is the average flow time?
A) fewer than or equal to 19 days
B) greater than 19 days but fewer than or equal to 21 days
C) greater than 21 days but fewer than or equal to 23 days
D) greater than 23 days