Multiple Choice
Table J.12
Consider the following problems in which six jobs must each be processed on two machines starting with machine 1 and then going to machine 2.The following processing times and due dates are in hours.
-Use the information in Table J.12.What is the makespan if the jobs are processed in FCFS order?
A) fewer than or equal to 30 hours
B) greater than 30 but fewer than or equal to 33 hours
C) greater than 33 but fewer than or equal to 36 hours
D) greater than 36 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q6: What are single-dimension scheduling rules? Provide examples
Q9: Table J.4<br>Workstation 1 has five jobs waiting
Q11: Table J.2<br>Suppose that the following six jobs
Q19: Table J.2<br>Suppose that the following six jobs
Q44: Table J.5<br>The following three jobs just arrived
Q50: _ is a priority sequencing rule that
Q52: Table J.11<br>Work center Q45 has four jobs
Q59: _ specify the job processing sequence when
Q101: The sum of scheduled receipts for all
Q118: Table J.10<br>A workstation has six jobs waiting