Table J.4
Workstation 1 has five jobs waiting to be processed.It is now time 0,and times are expressed in terms of days.All pertinent data are given in the following table.
-Using the information in Table J.4 and the SPT rule,what is the average days past due?
A) fewer than or equal to 1.0
B) greater than 1.0 but fewer than or equal to 2.0
C) greater than 2.0 but fewer than or equal to 3.0
D) greater than 3.0
Correct Answer:

Verified
Correct Answer:
Verified