Multiple Choice
Garman observes a worker assembling peanut valves and records the data displayed in the table.What is the select time for this job element?
A) 15 seconds
B) 20 seconds
C) 25 seconds
D) 30 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q53: An industrial engineer is conducting a time
Q59: An analyst using a time study approach:<br>A)
Q61: With the use of the methods time
Q63: A predetermined data approach to time standards
Q70: The predetermined data approach does not eliminate
Q77: The most commonly used method for setting
Q83: Table H.3<br>A worker was observed for four
Q83: A worker was observed for four cycles
Q95: Elemental standard time data cannot be used
Q106: A time study analyst has found the