The third step in Theory of Constraints application,"subordinate all other decisions to Step 2," means that the analyst should:
A) wait for authorization before proceeding with any system-wide changes.
B) schedule non-bottleneck processes to support the bottleneck schedule.
C) seek to increase capacity of only the bottleneck resources.
D) should seek to increase capacity of both the bottleneck and non-bottleneck resources.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Any factor that limits the performance of
Q55: Fun Vehicles, Inc. makes beach buggies on
Q77: The process with the least capacity is
Q123: Describe a process from your own personal
Q139: Table 7.8<br>King Supply makes four different types
Q141: Table 7.3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.3
Q142: Use the process flow diagram to determine
Q145: Figure 7.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Figure 7.1
Q146: Table 7.2 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.2
Q147: Table 7.7<br>A company makes four products that