Table 7.8
King Supply makes four different types of plumbing fixtures: W,X,Y and Z.The contribution margins for these products are: $70 for Product W,$60 for Product X,$90 for Product Y and $100 for Product Z.Fixed overhead is estimated at $5,500 per week.The manufacture of each fixture requires four machines,Machines #1,2,3 and 4.Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other.The processing requirements to make one unit of each product are shown in the table.Weekly product demand for the next planning period has been forecasted as follows: 70 Ws,60 Xs,50 Ys and 30 Zs. In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.8.Using the bottleneck method,what is the optimal product mix?
A) 70 W,60 X,90 Y,100 Z
B) 70 W,50 X,50 Y,30 Z
C) 70 W,60 X,47 Y,30 Z
D) 70 W,47 X,50 Y,30 Z
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Any factor that limits the performance of
Q77: The process with the least capacity is
Q111: The first step in applying the Theory
Q123: Describe a process from your own personal
Q134: Table 7.2 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.2
Q135: Table 7.5<br>A company makes four products that
Q136: Balance the assembly line for the tasks
Q141: Table 7.3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.3
Q142: Use the process flow diagram to determine
Q143: The third step in Theory of Constraints