Multiple Choice
Table 7.2 The figure above shows the process for paying tuition at a major university.Students are provided their bill for the next term for review,then routed to different tables for questions to be answered before finally paying their tuition at E.The numbers in parentheses are the time in minutes for each step of the process.
-Use the information in Table 7.2.What is the capacity for the A-B-C-E process route?
A) 10 students per hour
B) 6 student per hour
C) 3.5 students per hour
D) 2.9 students per hour
Correct Answer:

Verified
Correct Answer:
Verified
Q29: To generate the maximum output, the cycle
Q45: According to the Theory of Constraints,the four
Q47: Instead of producing products with the highest
Q49: The process with the least capacity is
Q51: Table 7.7<br>A company makes four products that
Q52: Table 7.7<br>A company makes four products that
Q75: What is a Drum-Buffer-Rope system for planning
Q88: Line balancing strives to create workstations so
Q117: According to the Theory of Constraints, all
Q122: The fifth step in Theory of Constraints