Multiple Choice
Table 7.5
A company makes four products that have the following characteristics: Product A sells for $50 but needs $10 of materials and $15 of labor to produce;Product B sells for $75 but needs $30 of materials and $15 of labor to produce;Product C sells for $100 but needs $50 of materials and $30 of labor to produce;Product D sells for $150 but needs $75 of materials and $40 of labor to produce.The processing requirements for each product on each of the four machines are shown in the table. Work centers W,X,Y,and Z are available for 40 hours per week and have no setup time when switching between products.Market demand for each product is 80 units per week.In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.5.Using the traditional method,what is the optimal product mix (consider variable costs only-overhead is not included in this profit calculation) ?
A) 71 A,80B,80C,80 D
B) 80A,72B,80C,80D
C) 80A,80B,60C,80D
D) 80A,80B,80C,70D
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Balance the line in order to achieve
Q25: Table 7.9<br>Balance the following line for an
Q26: Table 7.6<br>Burdell Industries makes four different models
Q27: According to the Theory of Constraints,the four
Q29: Table 7.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.1
Q30: Table 7.8<br>King Supply makes four different types
Q31: Table 7.2 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.2
Q32: Table 7.15<br>The Terminal Company is attempting to
Q33: Table 7.3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.3
Q52: A mixed-model line produces several items belonging