Multiple Choice
Table 7.8
King Supply makes four different types of plumbing fixtures: W,X,Y and Z.The contribution margins for these products are: $70 for Product W,$60 for Product X,$90 for Product Y and $100 for Product Z.Fixed overhead is estimated at $5,500 per week.The manufacture of each fixture requires four machines,Machines #1,2,3 and 4.Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other.The processing requirements to make one unit of each product are shown in the table.Weekly product demand for the next planning period has been forecasted as follows: 70 Ws,60 Xs,50 Ys and 30 Zs. In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.8.Using the bottleneck method,which product should be scheduled first?
A) Fixture W
B) Fixture X
C) Fixture Y
D) Fixture Z
Correct Answer:

Verified
Correct Answer:
Verified
Q25: Table 7.9<br>Balance the following line for an
Q26: Table 7.6<br>Burdell Industries makes four different models
Q27: According to the Theory of Constraints,the four
Q28: Table 7.5<br>A company makes four products that
Q29: Table 7.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.1
Q31: Table 7.2 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.2
Q32: Table 7.15<br>The Terminal Company is attempting to
Q33: Table 7.3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.3
Q34: Table 7.13<br>The following information is given about
Q35: Table 7.11<br>The Pennsylvania Appliance Company is installing