Multiple Choice
Table 7.5
A company makes four products that have the following characteristics: Product A sells for $50 but needs $10 of materials and $15 of labor to produce;Product B sells for $75 but needs $30 of materials and $15 of labor to produce;Product C sells for $100 but needs $50 of materials and $30 of labor to produce;Product D sells for $150 but needs $75 of materials and $40 of labor to produce.The processing requirements for each product on each of the four machines are shown in the table. Work centers W,X,Y,and Z are available for 40 hours per week and have no setup time when switching between products.Market demand for each product is 80 units per week.In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.5.Using the bottleneck method,in what sequence should products be scheduled for production?
A) D.C.B.A
B) D,C,A,B
C) C,D,A,B
D) C,D,B,A
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which one of the following statements about
Q44: _ is the total time taken from
Q51: Table 7.7<br>A company makes four products that
Q52: Table 7.7<br>A company makes four products that
Q56: Table 7.13<br>The following information is given about
Q57: Table 7.7<br>A company makes four products that
Q60: Table 7.11<br>The Pennsylvania Appliance Company is installing
Q66: A bottleneck is an operation that has
Q112: The balance delay is the amount by
Q117: According to the Theory of Constraints, all