Burdell Industries makes four different models of computer printers: the E-1000,the S-2000,the P-2000 and the N-1000.The E-1000 sells for $200 and has $40 in parts and $40 in labor;the S-2000 sells for $150 and requires $30 in parts and $30 in labor;the P-2000 sells for $100 and has $20 in parts and $20 in labor;and the N-1000 sells for $75 but requires only $10 of parts and $10 of labor.Fixed overhead is estimated at $5,000 per week.The manufacture of each printer requires four machines,Machines #1,2,3 and 4.Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other.The processing requirements to make one unit of each product are shown in the table.Weekly product demand for the next planning period has been forecasted as follows: 80 E-1000s;65 S-2000s;35 P-2000s;and 20 N-1000s. In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.6.Using the traditional method,what is the optimal product mix?
A) 120 E,90 S,60 P,55 N
B) 60 E,20 S,50 P,33 N
C) 80 E,65 S,35 P,5 N
D) 80 E,65 S,20 P,35 N
Correct Answer:

Verified
Correct Answer:
Verified
Q60: Table 7.11<br>The Pennsylvania Appliance Company is installing
Q61: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q62: Given the following data about an assembly
Q66: A bottleneck is an operation that has
Q66: Balance the assembly line for the tasks
Q67: Table 7.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.1
Q68: Table 7.9<br>Balance the following line for an
Q82: _ is a planning and control system
Q112: The balance delay is the amount by
Q125: Consider consecutive processes A-B-C, where process A