Multiple Choice
The process batch at the constraint in a drum-buffer-rope system should be:
A) the same size as that at any non-constraint.
B) the same size as the transfer batch.
C) of such a size as to maximize the number of setups for the constraint.
D) of such a size as to improve utilization of the constraint.
Correct Answer:

Verified
Correct Answer:
Verified