Multiple Choice
A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass,Inc.The desired output rate of 30 spreaders per hour will be achieved.The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled.This is the total productive time.Which of the following statements must be true?
A) The cycle time is 30 seconds per spreader.
B) The theoretical minimum number of stations is 10.
C) If the solution calls for 11 stations,the efficiency is 80%.
D) If the solution calls for 12 stations,the efficiency is 80%.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Line balancing is the assignment of work
Q22: Explain why a bottleneck limits system output.
Q87: The Theory of Constraints method is also
Q121: Lanny discovers that the bottleneck is the
Q121: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q125: Immediate predecessors are the smallest units of
Q127: Table 7.6<br>Burdell Industries makes four different models
Q129: Table 7.8<br>King Supply makes four different types
Q130: Table 7.5<br>A company makes four products that
Q131: Table 7.8<br>King Supply makes four different types