Multiple Choice
Keith assembles peanut valves and the recorded data is displayed in the table.What is the normal time for this job element if he is rated at 75%?
A) greater than or equal to 3 minutes
B) less than 3 minutes but greater than or equal to 2.6 minutes
C) less than 2.6 minutes but greater than or equal to 2.2 minutes
D) less than 2.2 minutes
Correct Answer:

Verified