Table 2.2 -Using Table 2.2,if the Expected Times for Activities A,G,and H

Question 83

Multiple Choice

Table 2.2 Table 2.2   -Using Table 2.2,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase? A) fewer than or equal to 2 weeks B) greater than 2 weeks but fewer than or equal to 4 weeks C) greater than 4 weeks but fewer than or equal to 6 weeks D) greater than 6 weeks
-Using Table 2.2,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?


A) fewer than or equal to 2 weeks
B) greater than 2 weeks but fewer than or equal to 4 weeks
C) greater than 4 weeks but fewer than or equal to 6 weeks
D) greater than 6 weeks