Table 2.12 -Using Table 2.12,if the Project's Normal Earliest Completion Time Is

Question 82

Multiple Choice

Table 2.12 Table 2.12   -Using Table 2.12,if the project's normal earliest completion time is to be reduced by two weeks,what is the minimum additional cost that will be incurred in achieving this two-week reduction? A) less than or equal to $1,000 B) greater than $1,000 but less than or equal to $1,500 C) greater than $1,500 but less than or equal to $2,000 D) greater than $2,000
-Using Table 2.12,if the project's normal earliest completion time is to be reduced by two weeks,what is the minimum additional cost that will be incurred in achieving this two-week reduction?


A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $1,500
C) greater than $1,500 but less than or equal to $2,000
D) greater than $2,000