Multiple Choice
Figure to accompany Table 2.9 Table 2.9
-If a decision is made to crash activity D in Table 2.9 by one week,what is the cost for this one week of crashing?
A) $3,000
B) $2,000
C) $2,500
D) This activity cannot be crashed.
Correct Answer:

Verified
Correct Answer:
Verified
Q56: Table 2.14<br>You are responsible for managing a
Q56: The work breakdown structure is a statement
Q57: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q59: Table 2.12 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.12
Q60: Table 2.14<br>You are responsible for managing a
Q61: Figure to accompany Table 2.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q63: Table 2.14<br>You are responsible for managing a
Q88: Heidi was part of a project team
Q105: The phase of project management that takes
Q111: A project tracking system should collect information