Table 2.14 You Are Responsible for Managing a Project with the Following

Question 56

Multiple Choice

Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks) . Table 2.14 You are responsible for managing a project with the following activities (times are given in weeks) .   -Using Table 2.14,what is the probability that the project will take 16 or more weeks to complete? A) less than or equal to 40% B) greater than 40% but less than or equal to 55% C) greater than 55% but less than or equal to 70% D) greater than 70%
-Using Table 2.14,what is the probability that the project will take 16 or more weeks to complete?


A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%