Multiple Choice
Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 2.14,what is the probability that the project will take 16 or more weeks to complete?
A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%
Correct Answer:

Verified
Correct Answer:
Verified
Q51: Table 2.5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.5
Q52: In an activity-on-node [AON] network,the nodes represent
Q56: The work breakdown structure is a statement
Q57: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q58: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q59: Table 2.12 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.12
Q60: Table 2.14<br>You are responsible for managing a
Q61: Figure to accompany Table 2.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q88: Heidi was part of a project team
Q105: The phase of project management that takes