Multiple Choice
Garman observes a worker assembling peanut valves and records the data displayed in the table.What is the select time for this job element?
A) 15 seconds
B) 20 seconds
C) 25 seconds
D) 30 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q6: Table H.1<br>A worker was observed for four
Q23: A time study analysis was performed on
Q26: Table H.1<br>A worker was observed for four
Q37: The following times in seconds were observed
Q43: The gentleman farmer recorded the time it
Q47: To set a time standard for a
Q50: How can work standards be developed for
Q66: The method used most often for setting
Q92: The snap-back method of time study resets
Q100: The advantage of using the predetermined data