When Using the MTM Approach

Question 24

Multiple Choice

When using the MTM approach:


A) stopwatches are needed to time the elements that go together to make a task.
B) there is a problem of biased judgment because performance ratings are needed to derive standards.
C) an analyst consults tables that contain the select times for a variety of work elements.
D) new work methods can be compared without conducting a time study.