Multiple Choice
When using the MTM approach:
A) stopwatches are needed to time the elements that go together to make a task.
B) there is a problem of biased judgment because performance ratings are needed to derive standards.
C) an analyst consults tables that contain the select times for a variety of work elements.
D) new work methods can be compared without conducting a time study.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Keith assembles peanut valves and the recorded
Q20: Table H.3<br>A worker was observed for four
Q21: The key to creating a work standard
Q22: Garman observes a worker assembling peanut valves
Q23: A time study analysis was performed on
Q25: What is the impact of greater reliance
Q26: Table H.1<br>A worker was observed for four
Q27: The process of creating labor standards based
Q28: Table H.1<br>A worker was observed for four
Q29: A time study analyst is attempting to