Multiple Choice
Figure to accompany Table 7.1
Table 7.1
-Using the information shown in Table 7.1, what is the slack time for activity D?
A) 1
B) 4
C) 6
D) 7
Correct Answer:

Verified
Correct Answer:
Verified