Multiple Choice
Table 7.6
-Using Table 7.6, suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
A) zero days
B) one day
C) two days
D) three days
Correct Answer:

Verified
Correct Answer:
Verified
Q129: A project has three paths. A-B-C has
Q130: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9
Q131: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q132: Table 7.14<br>You are responsible for managing a
Q133: A good risk management plan will contain
Q134: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4
Q135: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q136: In making an estimate of the most
Q138: Table 7.10<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.10
Q139: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4