Multiple Choice
Figure 5.3
The figure above shows the process for customers arriving at Hobbies Unlimited for several advertised crafts demonstrations. After signing in, customers are routed to different locations in the store for the two different programs provided. The numbers in parentheses are the time in minutes for each step of the process.
-Use the information in Figure 5.3 What is the throughput time for the A-B-C-D-G routing?
A) 25 minutes
B) 70 minutes
C) 105 minutes
D) 60 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q97: Table 5.6<br>Balance the following line for an
Q98: Work should be released into the system
Q99: Balance delay could be described as the:<br>A)
Q100: Table 5.1<br>A company makes four products that
Q101: Figure 5.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.4
Q103: Balance the line in order to achieve
Q104: Which statement about transfer batch sizes is
Q105: Table 5.2<br>A company makes four products that
Q106: Table 5.2<br>A company makes four products that
Q107: _ is the amount by which efficiency