Figure 5.3
The figure above shows the process for customers arriving at Hobbies Unlimited for several advertised crafts demonstrations. After signing in, customers are routed to different locations in the store for the two different programs provided. The numbers in parentheses are the time in minutes for each step of the process.
-Use the information in Figure 5.3. How many customers can be processed through the A-B-C-D-G routing during a 4-hour evening session?
A) 48
B) 24
C) 32
D) 12
Correct Answer:

Verified
Correct Answer:
Verified
Q110: Figure 5.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.4
Q111: The first step in applying the Theory
Q112: The balance delay is the amount by
Q113: Table 5.3<br>King Supply makes four different types
Q114: Balance the assembly line for the tasks
Q116: Table 5.3<br>King Supply makes four different types
Q117: According to the Theory of Constraints, all
Q118: Figure 5.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.4
Q119: What are two ways a process manager
Q120: Table 5.7<br>The Terminal Company is attempting to