Solved

Consider the Following Production Process

Question 15

Essay

Consider the following production process.It is trying to meet a market demand of 500 units per week. Consider the following production process.It is trying to meet a market demand of 500 units per week.   Step 1: Material release schedule Step 2: Drilling (capacity is 500 units/week) Step 3: Tapping (capacity is 450 units/week) Step 4: Grinding (capacity is 600 units/week) Step 5: Coating (capacity is 400 units/week) Step 6: Inspection (capacity is 1000 units/week) a.Where should buffers be placed? b.Which resource is the drum? c.Where should the rope be placed? d.Which resource is the bottleneck? e.Which resource is the CCR? Step 1: Material release schedule
Step 2: Drilling (capacity is 500 units/week)
Step 3: Tapping (capacity is 450 units/week)
Step 4: Grinding (capacity is 600 units/week)
Step 5: Coating (capacity is 400 units/week)
Step 6: Inspection (capacity is 1000 units/week)
a.Where should buffers be placed?
b.Which resource is the drum?
c.Where should the rope be placed?
d.Which resource is the bottleneck?
e.Which resource is the CCR?

Correct Answer:

verifed

Verified

a.A constraint buffer should be placed b...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions