Table 5.1
A company makes four products that have the following characteristics: Product A sells for $50 but needs $10 of materials and $15 of labor to produce; Product B sells for $75 but needs $30 of materials and $15 of labor to produce; Product C sells for $100 but needs $50 of materials and $30 of labor to produce; Product D sells for $150 but needs $75 of materials and $40 of labor to produce. The processing requirements for each product on each of the four machines are shown in the table.
Work centers W, X, Y, and Z are available for 40 hours per week and have no setup time when switching between products. Market demand for each product is 80 units per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.1. Using the traditional method, which product should be scheduled first?
A) Product A
B) Product B
C) Product C
D) Product D
Correct Answer:

Verified
Correct Answer:
Verified
Q126: An assembly line has to perform 10
Q127: Table 5.1<br>A company makes four products that
Q128: Table 5.7<br>The Terminal Company is attempting to
Q129: Table 5.5<br>Balance the following line for an
Q130: Balance the assembly line using the following
Q131: What is the definition of "theoretical maximum
Q132: Table 5.4<br>The Superior Management Company assembles muffalettas
Q133: What are five of the seven key
Q134: Table 5.3<br>King Supply makes four different types
Q136: A line that produces several items belonging