An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is


A) 5.00.
B) 5.33.
C) 5.67.
D) 17.00.
E) 0.533.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q30: What are the three phases of a

Q31: A simple CPM network has three activities,A,B,and

Q35: What is the basic difference between PERT

Q58: A network consists of the following

Q60: WBS stands for which of the following

Q61: Which of the following statements regarding CPM

Q64: Which of these statements regarding time-cost tradeoffs

Q65: The network below represents a project being

Q80: A code of ethics especially for project

Q117: Shortening the project's duration by deleting unnecessary

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines