Multiple Choice
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500, the crash cost per period is
A) $500
B) $1,500
C) $750
D) $13,000
E) $15,000
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q5: Which of the following statements regarding PERT
Q17: In a PERT network, non-critical activities that
Q50: Slack is the amount of time an
Q91: Which of the following projects were completed
Q107: The standard deviation of project duration is
Q114: A project organization<br>A) is effective for companies
Q116: A project being analyzed by PERT has
Q118: Pirmin's Bike Shop is behind on
Q120: The critical path for the network
Q121: The network below represents a project being