Briefly define walkthrough and describe the role of each participant.

Free
(Essay)
4.8/5
(35)
Correct Answer:
Verified

A walkthrough is a peer group review of any product created during the systems development process.During the review users,management,and the development group participate through various roles.These roles are coordinator,presenter,user,secretary,standards bearer,and maintenance oracle.The coordinator is the person who plans the meeting and facilitates a smooth meeting process.The presenter is the individual who describes the work product to the group.Ensuring that the work product meets the needs of the project's customers is the role fulfilled by the user.The person taking notes and recording decisions or recommendations made by the group is the secretary.The standards bearer role is to ensure that the work product adheres to organizational technical standards.The maintenance oracle is the individual who reviews the work product in terms of future maintenance activities.

A peer group review of any product created during the system development process refers to:

Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
Verified

A

For each of the following walkthrough roles,match it with its description. -This person ensures that the work product adheres to organizational standards.

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

E

A benefit derived from the creation of an information system that can be measured in dollars and with certainty is a(n):

(Multiple Choice)
4.8/5
(34)

Match each of the following terms with its definition. -A cost resulting from the ongoing evolution and use of a system.

(Multiple Choice)
4.8/5
(33)

At a walkthrough meeting,the person (or group)who ensures that the work product meets the needs of the project's customers is referred to as the:

(Multiple Choice)
4.8/5
(35)

Referencing a walkthrough,the maintenance oracle ensures that the work product adheres to organizational technical standards.

(True/False)
4.8/5
(39)

__________ finds the amount of time required for the cumulative cash flow from a project to equal its initial and ongoing investment.

(Short Answer)
4.8/5
(35)

__________ is the process of assessing the development organization's ability to construct a proposed system.

(Short Answer)
4.9/5
(31)

To gain an understanding of the organization's ability to construct the proposed system is the purpose of:

(Multiple Choice)
4.9/5
(41)

A cost associated with an information system that can be measured in dollars and with certainty is referred to as a(n):

(Multiple Choice)
5.0/5
(35)

Economic feasibility is the process of identifying the financial benefits and costs associated with a development project.

(True/False)
4.9/5
(29)

Match each of the following feasibility criteria with its purpose. -To gain an understanding of the degree to which the proposed system will likely solve the business problems or take advantage of the opportunities outlined in the systems service request or project identification study.

(Multiple Choice)
4.8/5
(35)

What is a Project Scope Statement and Baseline Project Plan? How are they different?

(Essay)
4.9/5
(35)

__________ is the process of assessing the degree to which the potential time frame and completion dates for all major activities within a project meet organizational deadlines and constraints for affecting change.

(Short Answer)
4.9/5
(32)

The rate of return used to compute the present value of future cash flows refers to:

(Multiple Choice)
4.9/5
(32)

Increased flexibility is an intangible benefit.

(True/False)
4.9/5
(37)

Match each of the following terms with its definition. -The process of assessing the degree to which the potential time frame and completion dates for all major activities within a project meet organizational deadlines and constraints for affecting change.

(Multiple Choice)
4.9/5
(38)

During project initiation and planning,you should precisely define all benefits and costs related to a particular project.

(True/False)
4.9/5
(43)

The Explanation of Services is a short document prepared for the customer that describes what the project will deliver and outlines all work required to complete the project.

(True/False)
4.9/5
(30)