Exam 5: Initiating and Planning Systems Development Projects
Exam 1: The Systems Development Environment174 Questions
Exam 2: The Origins of Software150 Questions
Exam 3: Managing the Information Systems Project167 Questions
Exam 4: Identifying and Selecting Systems Development Projects170 Questions
Exam 5: Initiating and Planning Systems Development Projects175 Questions
Exam 6: Determining System Requirements148 Questions
Exam 7: Structuring System Process Requirements236 Questions
Exam 8: Structuring System Data Requirements153 Questions
Exam 9: Designing Databases177 Questions
Exam 10: Designing Forms and Reports155 Questions
Exam 11: Designing Interfaces and Dialogues180 Questions
Exam 12: Designing Distributed and Internet Systems164 Questions
Exam 13: System Implementation166 Questions
Exam 14: Maintaining Information Systems160 Questions
Exam 15: Object-Oriented Analysis and Design: Use Cases51 Questions
Exam 16: Object-Oriented Analysis and Design: Activity Diagrams9 Questions
Exam 17: Objected-Oriented Analysis and Design: Object Modeling-Class Diagrams32 Questions
Exam 18: Object-Oriented Analysis and Design: Sequence Diagrams35 Questions
Select questions type
Referencing the Management Issues section of the Baseline Project Plan,the communication plan provides a description of the team member roles and reporting relationships.
(True/False)
4.9/5
(35)
During project initiation and planning,potential tangible benefits may have to be considered intangible.
(True/False)
4.8/5
(44)
Match each of the following terms with its definition.
-A peer group review of any product created during the system development process.
(Multiple Choice)
4.9/5
(26)
Which of the following is NOT a major section of the Baseline Project Plan?
(Multiple Choice)
4.9/5
(33)
Referencing a walkthrough meeting,the __________ plans the meeting and facilitates a smooth meeting process.
(Short Answer)
4.9/5
(36)
The __________ is the rate of return used to compute the present value of future cash flows.
(Short Answer)
4.9/5
(27)
Which of the following would be classified as a tangible cost?
(Multiple Choice)
4.9/5
(35)
Assume a proposed system has a useful life of 5 years,one-time costs of $1,000,000,recurring costs of $250,000 per year,and tangible benefits of $750,000 per year.If the cost of capital is 10%,what is the overall NPV? Overall ROI? Break-even point?
(Essay)
4.8/5
(40)
__________ is the process of assessing potential legal and contractual ramifications due to the construction of a system.
(Short Answer)
4.8/5
(31)
A document prepared for the customer during project initiation and planning that describes what the project will deliver and outlines generally at a high level all work required to complete the project is the:
(Multiple Choice)
4.9/5
(31)
Variable costs are costs resulting from the ongoing evolution and use of a system.
(True/False)
4.9/5
(29)
Opening new markets and increasing sales opportunities is a tangible benefit.
(True/False)
4.8/5
(36)
At a walkthrough meeting,the person who reviews the work product in terms of future maintenance activities is referred to as the:
(Multiple Choice)
4.9/5
(29)
Intangible benefits are benefits associated with project start-up,development,or system start-up.
(True/False)
4.7/5
(32)
As a rule of thumb estimate,what percentage of the entire development effort should be devoted to the project initiation and planning process?
(Multiple Choice)
4.8/5
(39)
When conducting a technical risk assessment,which of the following is true?
(Multiple Choice)
4.9/5
(37)
A __________ is a peer group review of any product created during the systems development process.
(Short Answer)
4.7/5
(30)
The concept of comparing present cash outlays to future expected returns best defines:
(Multiple Choice)
4.8/5
(33)