Exam 34: Project Scheduling
Exam 1: The Nature of Software3 Questions
Exam 2: Software Engineering3 Questions
Exam 3: Software Process Structure4 Questions
Exam 4: Process Models4 Questions
Exam 5: Agile Development4 Questions
Exam 6: Human Aspects of Software Engineering4 Questions
Exam 7: Principles That Guide Practice4 Questions
Exam 8: Understanding Requirements4 Questions
Exam 9: Requirements Modeling: Scenario- Based Methods4 Questions
Exam 10: Requirements Modeling: Class- Based Methods4 Questions
Exam 11: Requirements Modeling: Behavior, Patterns, and Web/ Mobile Apps4 Questions
Exam 12: Design Concepts4 Questions
Exam 13: Architectural Design4 Questions
Exam 14: Component- Level Design6 Questions
Exam 15: User Interface Design5 Questions
Exam 16: Pattern- Based Design4 Questions
Exam 17: Webapp Design4 Questions
Exam 18: Mobileapp Design4 Questions
Exam 19: Quality Concepts4 Questions
Exam 20: Review Techniques4 Questions
Exam 21: Software Quality Assurance4 Questions
Exam 22: Software Testing Strategies4 Questions
Exam 23: Testing Conventional Applications4 Questions
Exam 24: Testing Object- Oriented Applications4 Questions
Exam 25: Testing Web Applications4 Questions
Exam 26: Testing Mobileapps4 Questions
Exam 27: Security Engineering4 Questions
Exam 28: Formal Modeling and Verification4 Questions
Exam 29: Software Configuration Management5 Questions
Exam 30: Product Metrics5 Questions
Exam 31: Project Management Concepts4 Questions
Exam 32: Process and Project Metrics5 Questions
Exam 33: Estimation for Software Projects4 Questions
Exam 34: Project Scheduling4 Questions
Exam 35: Risk Management4 Questions
Exam 36: Maintenance and Reengineering4 Questions
Exam 37: Software Process Improvement4 Questions
Exam 38: Emerging Trends in Software Engineering4 Questions
Select questions type
What is "earned value analysis" as it relates to project scheduling?
Free
(Essay)
4.9/5
(43)
Correct Answer:
Earned value is a measure of progress.It enables you to assess the "percent of completeness" of a project using quantitative analysis rather than rely on a gut feeling.
Approximately what percent of the project time line should be devoted to each of the activities listed below?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?
Free
(Essay)
4.8/5
(38)
Correct Answer:
Planning 2-3%
Analysis 10-25%
Design 20-25%
Coding 15-20%
Testing 30-40%
Expend more time in design because design is the place where quality is built into a product.
In software project scheduling work,what is a task (or activity)network?
Free
(Essay)
4.8/5
(34)
Correct Answer:
A task network is a graphic representation depicting software engineering task dependencies and the workflow for a project.