Exam 21: Software Quality Assurance
List the tasks performed by the SQA group.
-Prepare SQA plan for the project.
-Participate in the development of the project's software process description.
-Review software engineering activities to verify compliance with the defined software process.
-Audit designated software work products to verify compliance with those defined as part of the software process.
-Ensure that any deviations in software or work products are documented and handled according to a documented procedure.
-Record any evidence of noncompliance and reports them to management
What are the goals for the project SQA activities?
-Requirements quality
-Design quality
-Code quality
-Quality control effectiveness
Describe statistical quality assurance?
-Information about
-software defects is collected and categorized
-Each defect is traced back to its cause
-Using the Pareto principle (80% of the defects can be traced to 20% of the causes)isolate the "vital few" defect causes
-Move to correct the problems that caused the defects in the "vital few"