Exam 5: Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What is a work breakdown structure?

Free
(Multiple Choice)
5.0/5
(42)
Correct Answer:
Verified

B

The critical path in a CPM analysis is always the shortest path through the network.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

False

Slack activity time is the difference between the early start and the late finish of a project activity time.

Free
(True/False)
4.8/5
(38)
Correct Answer:
Verified

False

A simple project listing of five activities and their respective time estimates are presented below: A simple project listing of five activities and their respective time estimates are presented below:   Using CPM, which activities make up the critical path? Using CPM, which activities make up the critical path?

(Multiple Choice)
4.8/5
(44)

Breakthrough projects are those that provide fundamental improvements to existing products.

(True/False)
4.9/5
(46)

For an activity in a CPM analysis the early finish time is 20 and the late finish time is 20. Which of the following statements is true?

(Multiple Choice)
4.9/5
(41)

You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. What are the three costs per unit of time to expedite each activity? You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. What are the three costs per unit of time to expedite each activity?

(Multiple Choice)
5.0/5
(34)

A work breakdown structure is used in project management but it is not used when the critical path method is involved.

(True/False)
4.7/5
(27)

You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

(Multiple Choice)
4.8/5
(42)

A project milestone is a specific event to be reached by a particular point in time.

(True/False)
4.9/5
(38)

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

(Multiple Choice)
4.8/5
(40)

The second step in managing a project is writing the statement of work.

(True/False)
4.9/5
(39)

You have just used the network planning model and found the critical path length is 60 days and there are two critical paths. The standard deviation of the first critical path is 10 days and the s.d. of the second critical path is 15 days. The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy)

(Multiple Choice)
4.8/5
(32)

A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.

(True/False)
4.7/5
(42)

One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.

(True/False)
4.9/5
(38)

A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

(Multiple Choice)
4.8/5
(36)

A simple project listing of five activities, their predecessors, and their respective time estimates are presented below: A simple project listing of five activities, their predecessors, and their respective time estimates are presented below:   Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)? Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?

(Multiple Choice)
4.8/5
(41)

A matrix project structure is often referred to as a "skunkworks."

(True/False)
4.7/5
(41)

An advantage of a pure project where self-contained teams work full time on a project is which of the following?

(Multiple Choice)
4.9/5
(39)

CPM is an abbreviation for critical path method.

(True/False)
5.0/5
(43)
Showing 1 - 20 of 75
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)