Exam 5: Projects
Exam 1: Operations and Supply Chain Management73 Questions
Exam 2: Strategy and Sustainability49 Questions
Exam 3: Forecasting94 Questions
Exam 4: Strategic Capacity Management58 Questions
Exam 5: Projects75 Questions
Exam 6: Manufacturing Processes59 Questions
Exam 7: Service Processes83 Questions
Exam 8: Sales and Operations Planning61 Questions
Exam 9: Material Requirements Planning86 Questions
Exam 10: Quality Management and Six Sigma136 Questions
Exam 11: Inventory Management105 Questions
Exam 12: Lean Supply Chains74 Questions
Exam 13: Global Sourcing and Procurement70 Questions
Exam 14: Location, Logistics, and Distribution57 Questions
Select questions type
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:
Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?

(Multiple Choice)
4.8/5
(41)
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?
(Multiple Choice)
4.9/5
(29)
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:
Using CPM, which activities make up the critical path?

(Multiple Choice)
4.7/5
(40)
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.
(True/False)
4.8/5
(39)
Which of the following is a graphic project report used in project management?
(Multiple Choice)
4.8/5
(38)
You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs associated with transferring the workers are an example of project indirect costs.
(True/False)
4.7/5
(34)
The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.
(True/False)
4.8/5
(37)
When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
(True/False)
4.9/5
(38)
In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?
(Multiple Choice)
4.7/5
(44)
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?


(Multiple Choice)
4.8/5
(39)
PERT is an abbreviation for which of the following methodologies?
(Multiple Choice)
4.9/5
(39)
Earned value management (EVM) is a technique for measuring project progress in an objective manner.
(True/False)
4.9/5
(28)
Below are the data for a Time-Cost CPM Scheduling analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost? 

(Multiple Choice)
4.9/5
(39)
One of the advantages of a functional project organizational structure is that a team member can work on several projects.
(True/False)
4.9/5
(41)
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.
(True/False)
4.7/5
(26)
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?


(Multiple Choice)
4.7/5
(38)
The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.
(True/False)
4.7/5
(34)