Exam 3: Cost Behavior
Exam 1: Introduction to Cost Management154 Questions
Exam 2: Basic Cost Management Concepts191 Questions
Exam 3: Cost Behavior187 Questions
Exam 4: Activity-Based Costing202 Questions
Exam 5: Product and Service Costing: Job-Order System142 Questions
Exam 6: Process Costing176 Questions
Exam 7: Allocating Costs of Support Departments and Joint Products160 Questions
Exam 8: Budgeting for Planning and Control206 Questions
Exam 9: Standard Costing: a Functional-Based Control Approach119 Questions
Exam 10: Decentralization: Responsibility Accounting, Performance133 Questions
Exam 11: Strategic Cost Management124 Questions
Exam 12: Activity-Based Management143 Questions
Exam 13: The Balanced Scorecard: Strategic-Based Control114 Questions
Exam 14: Quality and Environmental Cost Management192 Questions
Exam 15: Lean Accounting and Productivity Measurement165 Questions
Exam 16: Cost-Volume-Profit Analysis129 Questions
Exam 17: Activity Resource Usage Model and Tactical Decision Making116 Questions
Exam 18: Pricing and Profitability Analysis150 Questions
Exam 19: Capital Investment120 Questions
Exam 20: Inventory Management: Economic Order Quantity, Jit, and the Theory of Constraints119 Questions
Select questions type
_________ are assumed to be the sole drivers of a traditional cost management system.
(Short Answer)
4.9/5
(38)
When Multiple regression is used, the user has a choice of using manual computation or using regression programs.
(True/False)
4.9/5
(34)
The level of activity performance where the amount of activity capacity needed corresponds to the level of efficiency required is called the activity capacity.
(True/False)
4.7/5
(36)
_________ are those acquired from outside sources where the terms of acquisition do not require any long-term commitments.
(Short Answer)
4.9/5
(45)
Longberry Corporation manufactures and sells party items. The following representative direct labor hours and production costs are provided for a four-month period: Month Direct Labor Hours Production Costs May 3,600 \ 15,000 June 4,800 17,500 July 6,000 20,000 August 4,800 17,500 Total 19,200 \ 70,000
Let
A = Fixed production costs per month
B = Variable production costs per direct labor hour
N = Number of months
X = Direct labor hours per month
Y = Total monthly production costs
S = Summation
Using the high-low method, what is the cost formula for estimating costs?
(Multiple Choice)
4.9/5
(44)
Fixed costs are costs that, in total, are constant within the relevant range as the level of the associated driver varies.
(True/False)
4.9/5
(36)
The _________ parameter is the point at which the mixed cost line intercepts the cost (vertical) axis.
(Short Answer)
4.8/5
(39)