Exam 12: Standard Costs and Balanced Scorecard
Exam 1: Managerial Accounting107 Questions
Exam 2: Managerial Cost Concepts and Cost Behaviour Analysis128 Questions
Exam 3: Job-Order Cost Accounting169 Questions
Exam 4: Process Cost Accounting146 Questions
Exam 5: Activity-Based Costing85 Questions
Exam 6: Decision-Making: Costvolumeprofit124 Questions
Exam 7: Incremental Analysis114 Questions
Exam 8: Alternative Inventory Costing Methods: a Decision-Making Perspective68 Questions
Exam 9: Pricing101 Questions
Exam 10: Budgetary Planning166 Questions
Exam 11: Budgetary Control and Responsibility Accounting167 Questions
Exam 12: Standard Costs and Balanced Scorecard130 Questions
Exam 13: Planning for Capital Investments92 Questions
Select questions type
A standard which represents an efficient level of performance that is attainable under expected operating conditions is called a(n)
(Multiple Choice)
4.7/5
(37)
The costing of inventories at standard cost for external financial statement reporting purposes is
(Multiple Choice)
4.8/5
(34)
It is possible that a company's financial statements may report inventories at
(Multiple Choice)
4.7/5
(35)
Each of the following may cause an unfavourable variable overhead budget variance EXCEPT
(Multiple Choice)
4.9/5
(37)
The budgeted overhead costs for standard hours allowed and the overhead costs applied to the product are the same amount
(Multiple Choice)
4.9/5
(47)
If actual direct material costs are greater than standard direct materials costs, it means that
(Multiple Choice)
4.8/5
(30)
A problem with placing excessive emphasis on labour efficiency can be
(Multiple Choice)
4.9/5
(36)
The difference between actual overhead costs and overhead costs applied is the
(Multiple Choice)
4.9/5
(40)
EKPN Co.produces wooden boxes.The company's standards per box require 6 boards, each costing $10 per board, and half of an hour of direct labour.The standard labour rate is $15 per hour.In August, EKPN Co.Purchased 12,000 boards for a total cost of $123,000.It used 11,500 boards to manufacture 1,900 boxes.Total labour hours were 1,000 hours, and total labour costs were $16,250. What was the labour quantity variance for August?
(Multiple Choice)
4.8/5
(29)
Which of the following is NOT considered an advantage of using standard costs?
(Multiple Choice)
4.9/5
(38)
EKPN Co.produces wooden boxes.The company's standards per box require 6 boards, each costing $10 per board, and half of an hour of direct labour.The standard labour rate is $15 per hour.In August, EKPN Co.Purchased 12,000 boards for a total cost of $123,000.It used 11,500 boards to manufacture 1,900 boxes.Total labour hours were 1,000 hours, and total labour costs were $16,250.What was the materials price variance for August?
(Multiple Choice)
4.9/5
(47)
Once set, normal standards should NOT be changed during the year.
(True/False)
4.8/5
(35)
An unfavourable labour quantity variance indicates that the actual number of direct labour hours worked was greater than the number of direct labour hours that should have been worked for the output attained.
(True/False)
4.8/5
(35)
When a company implements a balanced scorecard approach in its business,
(Multiple Choice)
4.7/5
(41)
When analyzing period end variance reports, if a variance amount is small the manager should
(Multiple Choice)
4.9/5
(38)
Showing 61 - 80 of 130
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)