Exam 11: The Basics of Capital Budgeting

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following statements is CORRECT?

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
Verified

E

The IRR of normal Project X is greater than the IRR of normal Project Y, and both IRRs are greater than zero. Also, the NPV of X is greater than the NPV of Y at the cost of capital. If the two projects are mutually exclusive, Project X should definitely be selected, and the investment made, provided we have confidence in the data. Put another way, it is impossible to draw NPV profiles that would suggest not accepting Project X.

Free
(True/False)
4.9/5
(51)
Correct Answer:
Verified

False

Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

Free
(Multiple Choice)
4.7/5
(41)
Correct Answer:
Verified

C

Projects S and L are equally risky, mutually exclusive, and have normal cash flows. Project S has an IRR of 15%, while Project L's IRR is 12%. The two projects have the same NPV when the WACC is 7%. Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(39)

Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value will be lost if the IRR method is used. WACC: 10.25%\quad 10.25 \% Year 0 - \2 ,050 - \4 ,300 1 \7 50 1,500 2 \7 60 \1 ,518 3 \7 70 \1 ,536 4 \7 80 \1 ,554 a. $134.79 \$134.79 b. $141.89\$ 141.89 c. $149.36\$ 149.36 d. $164.29 \$164.29 e. $205.36\$205.36

(Short Answer)
4.8/5
(38)

Under certain conditions, a project may have more than one IRR. One such condition is when, in addition to the initial investment at time = 0, a negative cash flow (or cost) occurs at the end of the project's life.

(True/False)
5.0/5
(45)

Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

(Multiple Choice)
4.8/5
(31)

Noe Drilling Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the MIRR. If the decision is made by choosing the project with the higher IRR rather than the one with the higher MIRR, how much, if any, value will be forgone, i.e., what's the NPV of the chosen project versus the maximum possible NPV? Note that (1) "true value" is measured by NPV, and (2) under some conditions the choice of IRR vs. MIRR will have no effect on the value lost. Noe Drilling Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the MIRR. If the decision is made by choosing the project with the higher IRR rather than the one with the higher MIRR, how much, if any, value will be forgone, i.e., what's the NPV of the chosen project versus the maximum possible NPV? Note that (1) true value is measured by NPV, and (2) under some conditions the choice of IRR vs. MIRR will have no effect on the value lost.

(Multiple Choice)
4.8/5
(40)

The phenomenon called "multiple internal rates of return" arises when two or more mutually exclusive projects that have different lives are being compared.

(True/False)
4.8/5
(45)

Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(36)

Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC:\text {WACC:} \quad 8.75%8.75 \% Year 0 - \1 ,100 - \2 ,200 1 \3 75 725 2 \3 75 \7 25 3 \3 75 \7 25 4 \3 75 \7 25 a. $32.12\$ 32.12 b. $35.33\$ 35.33 c. $38.87\$ 38.87 d. $40.15\$ 40.15 e. $42.16\$ 42.16

(Short Answer)
4.9/5
(30)

Cornell Enterprises is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's projected NPV can be negative, in which case it will be rejected. WACC: 10.00%\quad 10.00 \% Year Cash flows 0 - \1 ,050 1 \4 50 2 \4 60 3 \4 70 a $92.37\$ 92.37 b. $96.99\$ 96.99 c. $101.84\$ 101.84 d. $106.93\$ 106.93 e. $112.28\$ 112.28

(Short Answer)
4.8/5
(38)

Projects C and D are mutually exclusive and have normal cash flows. Project C has a higher NPV if the WACC is less than 12%, whereas Project D has a higher NPV if the WACC exceeds 12%. Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(36)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(41)

The NPV method is based on the assumption that projects' cash flows are reinvested at the project's risk-adjusted cost of capital.

(True/False)
4.7/5
(42)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(37)

Susmel Inc. is considering a project that has the following cash flow data. What is the project's payback? Year Cash flows 0 - \5 00 1 \1 50 2 \2 00 3 \3 00 a 2.032.03 years b. 2.252.25 years c. 2.502.50 years d. 2.752.75 years e. 3.033.03 years

(Short Answer)
4.9/5
(26)

Taggart Inc. is considering a project that has the following cash flow data. What is the project's payback? Year Cash flows 0 - \1 ,150 1 \5 00 2 \5 00 3 \5 00 a. 1.861.86 years b. 2.072.07 years c. 2.302.30 years d. 2.53 years e. 2.782.78 years

(Short Answer)
4.7/5
(44)

Projects A and B are mutually exclusive and have normal cash flows. Project A has an IRR of 15% and B's IRR is 20%. The company's WACC is 12%, and at that rate Project A has the higher NPV. Which of the following statements is CORRECT?

(Multiple Choice)
4.7/5
(38)

Assuming that their NPVs based on the firm's cost of capital are equal, the NPV of a project whose cash flows accrue relatively rapidly will be more sensitive to changes in the discount rate than the NPV of a project whose cash flows come in later in its life.

(True/False)
4.8/5
(33)
Showing 1 - 20 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)