Exam 11: The Basics of Capital Budgeting
Exam 1: An Overview of Financial Management97 Questions
Exam 2: Financial Markets and Institutions33 Questions
Exam 3: Financial Statements, Cash Flow, and Taxes118 Questions
Exam 4: Analysis of Financial Statements121 Questions
Exam 5: The Value of Money164 Questions
Exam 6: Interest Rates80 Questions
Exam 7: Bonds and Their Valuation91 Questions
Exam 8: Risk and Rates of Return145 Questions
Exam 9: Stocks and Their Valuation86 Questions
Exam 10: The Cost of Capital94 Questions
Exam 11: The Basics of Capital Budgeting94 Questions
Exam 12: Cash Flow Estimation and Risk Analysis65 Questions
Exam 13: Capital Structure and Leverage81 Questions
Exam 15: Working Capital Management122 Questions
Exam 16: Financial Planning and Forecasting36 Questions
Exam 17: Multinational Financial Management50 Questions
Exam 18: Financial and Operating Leverage: Analysis and Calculation67 Questions
Select questions type
Other things held constant, an increase in the cost of capital will result in a decrease in a project's IRR.
(True/False)
4.9/5
(37)
The primary reason that the NPV method is conceptually superior to the IRR method for evaluating mutually exclusive investments is that multiple IRRs may exist, and when that happens, we don't know which IRR is relevant.
(True/False)
4.8/5
(43)
Which of the following statements is CORRECT? Assume that all projects being considered have normal cash flows and are equally risky.
(Multiple Choice)
4.8/5
(37)
Normal Projects S and L have the same NPV when the discount rate is zero. However, Project S's cash flows come in faster than those of L. Therefore, we know that at any discount rate greater than zero, L will have the higher NPV.
(True/False)
4.8/5
(38)
The IRR method is based on the assumption that projects' cash flows are reinvested at the project's risk-adjusted cost of capital.
(True/False)
4.9/5
(39)
Lasik Vision Inc. recently analyzed the project whose cash flows are shown below. However, before Lasik decided to accept or reject the project, the Federal Reserve took actions that changed interest rates and therefore the firm's WACC. The Fed's action did not affect the forecasted cash flows. By how much did the change in the WACC affect the project's forecasted NPV? Note that a project's projected NPV can be negative, in which case it should be rejected. Old WACC: 8.00\% New WACC: 11.25\%
Year Cash flows 0 - \1 ,00 1 \4 1 2 \4 10 3 \4 10
a.
b.
c.
d.
e.
(Short Answer)
4.8/5
(40)
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.
(Multiple Choice)
4.9/5
(37)
Both the regular and the modified IRR (MIRR) methods have wide appeal to professors, but most business executives prefer the NPV method to either of the IRR methods.
(True/False)
4.8/5
(39)
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.
(Multiple Choice)
4.9/5
(39)
Maxwell Feed & Seed is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC (and even negative), in which case it will be rejected. Year Cash flows 0 - \9 ,500 1 \2 ,000 2 \2 ,025 3 \2 ,050 4 \2 ,075 5 \3 2,100
a
b.
c.
d.
e.
(Short Answer)
4.9/5
(36)
Projects A and B have identical expected lives and identical initial cash outflows (costs). However, most of one project's cash flows come in the early years, while most of the other project's cash flows occur in the later years. The two NPV profiles are given below:
Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(41)
Last month, Lloyd's Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project, the Federal Reserve took actions that changed interest rates and therefore the firm's WACC. The Fed's action did not affect the forecasted cash flows. By how much did the change in the WACC affect the project's forecasted NPV? Note that a project's projected NPV can be negative, in which case it should be rejected. Old WACC: 10.00\% New WACC: 11.25\%
Year Cash flows 0 - \1 ,100 1 \4 10 2 \4 10 3 \4 10
Old NPV =\ 19.61 New NPV =-\ 2.42 Change =-\ 22.03
(Short Answer)
4.9/5
(43)
Showing 81 - 94 of 94
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)