Exam 14: Products and Processes
Exam 1: Introduction to Materials Management30 Questions
Exam 2: Production Planning System30 Questions
Exam 3: Master Scheduling29 Questions
Exam 4: Material Requirements Planning30 Questions
Exam 5: Capacity Management30 Questions
Exam 6: Production Activity Control29 Questions
Exam 7: Purchasing30 Questions
Exam 8: Forecasting30 Questions
Exam 9: Inventory Fundamentals30 Questions
Exam 10: Order Quantities26 Questions
Exam 11: Independent Demand Ordering Systems29 Questions
Exam 12: Physical Inventory and Warehouse Management30 Questions
Exam 13: Physical Distribution30 Questions
Exam 14: Products and Processes30 Questions
Exam 15: Just-In-Time Manufacturing and Lean Production30 Questions
Exam 16: Total Quality Management30 Questions
Select questions type
Job ________ expands a worker's job by clustering similar or related tasks into one job.
(Multiple Choice)
4.7/5
(42)
A process flow diagram shows graphically and sequentially the various steps and operations that make up a process.
(True/False)
4.8/5
(32)
A manufacturer has a choice of purchasing and installing a heat- treating oven or having the heat treating done by an outside supplier. For the in- house treatment the fixed costs are $28,000 with a variable cost of $10. To purchase outside, the variable costs are $17 per unit.
What is the cost equalization point. Should the company have the heat treating done outside if the annual volume is 3,000 units? 5,000 units?
(Essay)
4.9/5
(35)
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is $30 per hour. Determine the fixed cost, the variable cost and the total cost and unit cost for a lot of 500.
(Essay)
4.9/5
(31)
________record in sequence only the main operation and inspections.
(Multiple Choice)
4.9/5
(34)
Showing 21 - 30 of 30
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)