Exam 11: Process Design and Analysis
Exam 1: Introduction78 Questions
Exam 2: Strategy56 Questions
Exam 3: Design of Products and Services71 Questions
Exam 4: Projects108 Questions
Exam 5: Strategic Capacity Management69 Questions
Exam 6: Learning Curves57 Questions
Exam 7: Manufacturing Processes52 Questions
Exam 8: Facility Layout60 Questions
Exam 9: Service Processes71 Questions
Exam 10: Waiting Line Analysis and Simulation77 Questions
Exam 11: Process Design and Analysis67 Questions
Exam 12: Six Sigma Quality70 Questions
Exam 13: Statistical Quality Control64 Questions
Exam 14: Lean Supply Chains85 Questions
Exam 15: Logistics, Distribution, and Transportation61 Questions
Exam 16: Global Sourcing and Procurement73 Questions
Exam 17: The Internet of Things and Erp40 Questions
Exam 18: Forecasting102 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management104 Questions
Exam 21: Material Requirements Planning91 Questions
Exam 22: Workcenter Scheduling125 Questions
Select questions type
A job is said to be enlarged horizontally if the worker is involved in planning, organizing, and inspecting his or her own work.
(True/False)
4.7/5
(33)
If you want to reduce process flow time, it has been suggested that you can perform activities in the process in parallel.
(True/False)
4.9/5
(37)
To reduce process throughput time, you might try which of the following actions?
(Multiple Choice)
4.9/5
(35)
Throughput rate of a production process is the amount of time a unit spends actually being worked on.
(True/False)
4.8/5
(39)
Which of the following terms describes a ratio of the actual output of a process relative to some standard.
(Multiple Choice)
4.8/5
(37)
Starving occurs when the firm must stop because there are no customer orders.
(True/False)
4.7/5
(32)
An advantage of a make-to-stock process is which of the following?
(Multiple Choice)
4.8/5
(31)
One way to categorize a process is to determine whether it is a multiple-stage or a single-stage process.
(True/False)
4.7/5
(36)
If you want to reduce process flow time, it has been suggested that you can reduce interruptions in the production process.
(True/False)
4.8/5
(42)
Little's law says there is a long-term relationship among the inventory, throughput, and flow time of a production system in steady state.
(True/False)
4.8/5
(31)
Process analysis can help answer many important questions such as why change in a process is necessary.
(True/False)
4.9/5
(42)
Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into Process B. Output from B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C. Suppose further that Process A receives input at the rate of 30 per hour. Which process will be experiencing starving?
(Multiple Choice)
4.8/5
(31)
Inventory turn is the cost of goods sold divided by the average inventory value.
(True/False)
4.9/5
(41)
Job design is defined as the function of specifying the work activities of an individual or group in an organizational setting.
(True/False)
4.9/5
(32)
Which of the following production process terms best describes a situation where the activities in the stage must stop because there is no place to deposit the item just completed?
(Multiple Choice)
4.8/5
(41)
When we use a make-to-stock production process, we control our production based on a desired amount of finished goods inventory.
(True/False)
4.9/5
(45)
Value-added time is the total of all the time that work is being done on the unit plus all the transfer times.
(True/False)
4.7/5
(38)
Process analysis can help answer many important questions such as how many customers can a process handle per hour.
(True/False)
4.8/5
(32)
A process flowchart uses which of the following symbols to represent storage areas or queues in a flow diagram?
(Multiple Choice)
4.8/5
(32)