Exam 23: Development: The Dynamics of Creating Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When a developer decides to break down the project design into sequential phases and begins construction before the last phases of the design are complete, this procedure is more commonly referred to as

(Multiple Choice)
4.9/5
(36)

When construction costs exceed the amount of the construction loan, a developer may seek to cover the gap using mezzanine financing. All of the following statements regarding mezzanine debt are true EXCEPT:

(Multiple Choice)
4.7/5
(38)

Development involves a complex organization of many moving parts. Which of the following choices is often viewed as the single greatest cause of project delays and cost overruns?

(Multiple Choice)
4.9/5
(37)

In considering the main components of a construction budget, which costs would be expected to constitute the largest portion of a development project's expense?

(Multiple Choice)
4.8/5
(29)

Suppose that a developer pre-leases space to a financially strong, national tenant such as Home Depot, without having yet built the structure in which they will be leasing space. This is more commonly referred to as a:

(Multiple Choice)
4.9/5
(42)

After construction has been completed, a developer may decide to seek additional financing. If current interest rates are relatively high, but the developer expects them to decline in the near future, the developer would most likely seek financing in the form of a:

(Multiple Choice)
4.9/5
(36)

A developer's selection of an architect is a vital step in the development process as the architect fulfills a number of important roles throughout the life of the project. As compensation for contributions in the design phase, the architect is often given a percentage of the construction cost. For moderately complex designs, the average compensation will be:

(Multiple Choice)
4.8/5
(34)

The construction budget has six main components: land costs, hard costs, construction soft costs, marketing soft costs, developer's fee, and total construction financing costs. Which of the following would be considered a hard cost?

(Multiple Choice)
4.8/5
(36)

The developer will face a variety of costs throughout the project's life. Which of the following would be classified as a soft cost?

(Multiple Choice)
4.9/5
(39)

The expertise of several types of engineers must be coordinated by the architect in bringing together the final structure design. Which of the following types of engineers is responsible for specifications to achieve safety and stability for a structure's foundation?

(Multiple Choice)
4.7/5
(39)

The second stage of the development process requires an analysis of the project's feasibility. The developer will typically begin this stage of the development process with which of the following types of analysis?

(Multiple Choice)
4.7/5
(32)

Which of the following types of engineers is responsible for providing specifications and design for the HVAC system and other building systems?

(Multiple Choice)
4.9/5
(32)