Exam 7: Integer Linear Programming
Exam 1: Introduction36 Questions
Exam 2: An Introduction to Linear Programming46 Questions
Exam 3: Linear Programming: Sensitivity Analysis and Interpretation of Solution36 Questions
Exam 4: Linear Programming Applications in Marketing, Finance, and Operations Management36 Questions
Exam 5: Advanced Linear Programming Applications30 Questions
Exam 6: Distribution and Network Models55 Questions
Exam 7: Integer Linear Programming41 Questions
Exam 8: Nonlinear Optimization Models44 Questions
Exam 9: Project Scheduling: Pertcpm47 Questions
Exam 10: Inventory Models43 Questions
Exam 11: Waiting Line Models40 Questions
Exam 12: Simulation43 Questions
Exam 13: Decision Analysis36 Questions
Exam 14: Multicriteria Decisions39 Questions
Exam 15: Forecasting38 Questions
Exam 16: Markov Processes31 Questions
Select questions type
Some linear programming problems have a special structure that guarantees the variables will have integer values.
(True/False)
4.9/5
(33)
If Project 5 must be completed before Project 6, the constraint would be x5- x6 0.
(True/False)
5.0/5
(34)
The solution to the LP Relaxation of a minimization problem will always be less than or equal to the value of the integer program minimization problem.
(True/False)
4.8/5
(32)
The constraint x1 + x2 + x3 + x4 F 2 means that two out of the first four projects must be selected.
(True/False)
4.8/5
(33)
Simplon Manufacturing must decide on the processes to use to produce 1650 units. If machine 1 is used, its production will be between 300 and 1500 units. Machine 2 and/or machine 3 can be used only if machine 1's production is at least 1000 units. Machine 4 can be used with no restrictions.
(HINT: Use an additional 0 - 1 variable to indicate when machines 2 and 3 can be used.)

(Essay)
4.9/5
(37)
Let x1 and x2 be 0 - 1 variables whose values indicate whether projects 1 and 2 are not done or are done. Which answer below indicates that project 2 can be done only if project 1 is done?
(Multiple Choice)
4.8/5
(34)
Grush Consulting has five projects to consider. Each will require time in the next two quarters according to the table below.
Revenue from each project is also shown. Develop a model whose solution would maximize revenue, meet the time budget of 25 in the first quarter and 20 in the second quarter, and not do both projects C and D.

(Essay)
4.7/5
(37)
In a model involving fixed costs, the 0 - 1 variable guarantees that the capacity is not available unless the cost has been incurred.
(True/False)
4.8/5
(30)
If the acceptance of project A is conditional on the acceptance of project B, and vice versa, the appropriate constraint to use is a
(Multiple Choice)
4.8/5
(35)
The graph of a problem that requires x1 and x2 to be integer has a feasible region
(Multiple Choice)
4.8/5
(29)
Which of the following is the most useful contribution of integer programming?
(Multiple Choice)
4.8/5
(29)
If the optimal solution to the LP relaxation problem is integer, it is the optimal solution to the integer linear program.
(True/False)
4.8/5
(29)
The LP Relaxation contains the objective function and constraints of the IP problem, but drops all integer restrictions.
(True/False)
4.9/5
(36)
In a model, x1 0 and integer, x2 0, and x3 = 0, 1. Which solution would not be feasible?
(Multiple Choice)
4.8/5
(25)
The constraint x1-x2 = 0 implies that if project 1 is selected, project 2 cannot be.
(True/False)
4.8/5
(30)
If a problem has only less-than-or-equal-to constraints with positive coefficients for the variables, rounding down will always provide a feasible integer solution.
(True/False)
4.9/5
(36)
If the LP relaxation of an integer program has a feasible solution, then the integer program has a feasible solution.
(True/False)
4.8/5
(40)
Showing 21 - 40 of 41
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)