​Setting up a change control log to keep track of new system requirements is part of what PMBOK area?

Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
Verified

D

​In Microsoft Project if task B need to begin two days after task A started,you would use a task dependency of _______.

Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
Verified

B

​The _____ is the point at which the increased cash flow exactly pays off the costs of development and operation.

Free
(Short Answer)
4.9/5
(41)
Correct Answer:
Verified

breakeven point
payback period​

​Which of the following equations is correct for calculating early start time?

(Multiple Choice)
4.9/5
(32)

​Given the below figure what tasks are included in the critical path? ​Given the below figure what tasks are included in the critical path?

(Multiple Choice)
4.9/5
(41)

​Which of the following equations represents the present value (PV)of a discounted future amount (FA)at a discount rate (i)for multiple periods (n)? 

(Multiple Choice)
4.8/5
(32)

​In Microsoft Project a Tracking Gantt chart is useful to keep track of the resources on a project.

(True/False)
4.9/5
(43)

​The accumulation of yearly discounts based on a discount rate is called the ______.

(Short Answer)
4.8/5
(35)

​Which is NOT one of the characteristics of a quality software system?

(Multiple Choice)
4.9/5
(39)

​For a particular project the new system requires the installation of new servers.Managing this activity fits best in which project management area?

(Multiple Choice)
4.8/5
(37)

​In Microsoft Project the process (either manual or automated)which resolves resource conflicts is called ______.

(Short Answer)
4.9/5
(33)

​A project manager has purchased some training classes for JAVA programming for new members of his team.This would be considered to be part of which PM management area?

(Multiple Choice)
4.9/5
(38)

​The annual percentage rate that an amount of money is discounted to bring to a present value is called the _____.

(Short Answer)
4.9/5
(37)

​In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the critical path the total slack time is _____?

(Multiple Choice)
4.8/5
(43)

​List the nine PMBOK knowledge areas.

(Essay)
4.8/5
(35)

​Given the below figure,what is the 2 year ROI without discount? ​Given the below figure,what is the 2 year ROI without discount?

(Multiple Choice)
4.8/5
(33)

​In Microsoft Project a PERT/CPM chart view is called a _____  diagram.

(Short Answer)
4.9/5
(35)

​Which of the following is also referred to as the breakeven point?

(Multiple Choice)
4.9/5
(39)

​The latest time that a task can start on a project schedule without negative impacts to the overall schedule is called the ______.

(Short Answer)
4.7/5
(32)

​The most common way to determine the discount rate for NPV calculations is by _____.

(Multiple Choice)
4.8/5
(40)