Exam 6: Managing Is Projects and Creating Is Solutions

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A ________ is a detailed investigation and analysis of a proposed development project, to determine whether it is technically and economically possible.

(Multiple Choice)
4.8/5
(30)

According to Joey Peng, what is good on-the-job advice?

(Multiple Choice)
4.8/5
(35)

A/An _____ actually creates the system itself by coding and deploying the technical infrastructure of the system and programming it to perform required tasks.

(Multiple Choice)
4.7/5
(23)

What is action for knowing that risks will occur and ensuring that contingency plans are in place?

(Multiple Choice)
4.9/5
(41)

Intangible refers to:

(Multiple Choice)
4.8/5
(34)

A(n) __________ chart is used to show the sequences of project activities and to identify the critical path.

(Multiple Choice)
4.9/5
(40)

At a high level, the SDLC simply starts with an idea. We call this the:

(Multiple Choice)
4.7/5
(34)

A/An _____ diagram, which shows the order of various activities and by whom, and how they interact with the various system components as they occur in order.

(Multiple Choice)
4.7/5
(33)

With_____, the project team works with customers to progressively build the system from an initial outline specification using visual mock-ups of screens, diagrams of data relationships, and similar tools that help users see what is going to be built.

(Multiple Choice)
4.9/5
(29)

At which development phase does an organization finalize an IS and put it in place?

(Multiple Choice)
4.9/5
(38)

Which of the following is not a main activity of project time management?

(Multiple Choice)
4.9/5
(40)

This phase of the SDLC begins when an organization has the idea to build an information system.

(Multiple Choice)
5.0/5
(26)
Showing 81 - 92 of 92
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)