When the work is routine,fast-tracking rarely causes serious problems.
(True/False)
4.8/5
(33)
Allocating specific,limited resources to specific activities is called
(Multiple Choice)
4.9/5
(37)
The safety time added to chains other than the critical chain is called
(Multiple Choice)
4.8/5
(36)
Often it is beneficial to crash activities NOT on the critical path.
(True/False)
4.7/5
(29)
The variance of the normal time can be quite different from the variance of the crash time.
(True/False)
4.9/5
(31)
In general,steady state demand for human resources is highly desirable.
(True/False)
4.7/5
(43)
A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.
(True/False)
4.8/5
(30)
Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.
(True/False)
4.8/5
(30)
Good PM are able to estimate project task times with absolute certainty
(True/False)
4.9/5
(33)
When crashing a task,the usual assumption is that a task is crashed the full amount or none at all.
(True/False)
5.0/5
(35)
Starting the building phase before the design and planning phases is called
(Multiple Choice)
4.7/5
(40)
If resources were not scarce,the resource allocation problem would be concerned solely with profit maximization.
(True/False)
4.8/5
(33)
Fast-tracking a project is used primarily in the pharmaceutical industry.
(True/False)
4.9/5
(44)
A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.
(True/False)
5.0/5
(41)
A task has a normal duration of 9 days and a crash duration of 7 days.Its normal cost is $40 and its crash cost is $100.What is the crash cost per day?
(Multiple Choice)
4.8/5
(33)
The task duration with standard-practice resource usage is referred to as the
(Multiple Choice)
4.8/5
(32)
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
(True/False)
4.8/5
(39)
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project's duration?
(Multiple Choice)
4.8/5
(44)
Showing 21 - 40 of 46