Exam 7: Extension: Learning Curves
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
Ron has noted that the first accounting problem he did in a set of similar problems took him one hour, and the ninth problem took 24 minutes.
(A) Estimate Ron's learning curve.
(B) About how long did it take Ron to do his set of 10 problems?
Free
(Essay)
4.8/5
(39)
Correct Answer:
(A) The learning curve rate is approximately 75 percent.
(B) The total time for 10 problems using 75 percent is 60(5.589) = 335.34 minutes, or 5.589 hours, or 5 hours and 35.34 minutes.
To which worker would learning curves be most applicable?
Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
D
A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours. If a contract for 30 units is canceled after the first 20 units, approximately how much of the expected total direct labor will have been expended to that point?
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
A
A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data: UNIT PRODUCED TIME REQUIRED Second 5 hours Fourth 4 hours What is the learning curve percentage?
(Multiple Choice)
4.8/5
(37)
A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours. What is the average time per unit for the first 30 units?
(Multiple Choice)
4.8/5
(33)
A job has an 80 percent learning curve. If the first unit took 50 hours to complete, the third unit should take roughly how many hours?
(Multiple Choice)
4.8/5
(31)
Which one of the following would learning curves probably affect the least?
(Multiple Choice)
4.9/5
(29)
For an 80 percent learning curve, if the first unit requires 10 hours, the second unit will require 8 hours and the third 6.4 hours.
(True/False)
4.9/5
(48)
A learning percentage of 95 percent indicates greater learning than a percentage of 90 percent.
(True/False)
4.7/5
(39)
If the elapsed time for the task is short and the activity is somewhat routine, a modest amount of improvement occurs during the first few repetitions.
(True/False)
4.9/5
(46)
Suppose the first unit of output required 900 labor hours, and the second unit required only 810. At this rate, how many more units must be produced before labor requirements are less than 700 hours?
(Multiple Choice)
4.8/5
(32)
A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data: UNIT PRODUCED TIME REQUIRED Second 5 hours Fourth 4 hours How long did it take to produce the first unit?
(Multiple Choice)
4.8/5
(36)
How long would a job with a 70 percent learning curve and a time of 20 hours for the first unit require (approximately, in hours) for the third unit?
(Multiple Choice)
5.0/5
(35)
If an 80 percent curve is appropriate for a task and the first unit takes 10 hours, the average time for the first two units would be eight hours.
(True/False)
5.0/5
(36)
Which of the following is an example of a carryover effect?
(Multiple Choice)
4.9/5
(47)
Learning curves are mostly relevant for complex, new activities that have not been done often.
(True/False)
4.9/5
(39)
A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours. Approximately how long will it take to produce the 15th unit?
(Multiple Choice)
4.8/5
(39)
Which of the following is not a major caution or criticism of learning curves?
(Multiple Choice)
4.8/5
(37)
Developing work assignments in a job shop in a certain firm has a learning curve of 80 percent. If the second set of assignments takes 12 minutes, determine the length of time required for the following:
(A) the fifth set.
(B) sets 3, 4, and 5 together.
(Essay)
4.8/5
(36)
Sometimes improvements in labor requirements are more apparent than real because of:
(Multiple Choice)
4.7/5
(41)
Showing 1 - 20 of 68
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)